Civic Centre Resource Library – March 3

Bookmark and Share

The weather is slowing warming up, construction at the Civic Centre Resource Library is coming along very well. Painting work is ongoing at the main floor. Ceiling work is nearing completion. Ceiling baffles and lighting installation are ongoing in the teen and adult areas. Bench seating is being installed. Tile work is ongoing at the washrooms.

1

Painting work is ongoing at the main floor.

2

Above ceiling work is nearing completion.

3

Ceiling baffles and lighting installation are ongoing in the teen and adult areas.

4

Tile work is ongoing at the washrooms.

5

Bench seating installation in ongoing.

6

Wood paneling work is ongoing above the children's area.

7

Interior light fixtures have arrived on site and installation is ongoing.

 

 

Civic Centre Resource Library – Feb. 12

Bookmark and Share

This week at the Civic Centre Resource Library, framing and drywall installation are progressing throughout the building. Painters continue to complete spraying the ceiling and are working on the first coat of the walls at the teen area and office areas on the ground floor. Light fixture installation has started at the adult collection area. Tile work has commenced at the washrooms.

1

View of collaboration rooms at the west. Mechanical work is almost complete in the ceiling space.

ceiling

Painting work has progressed at the ceiling and bulkheads.

Light fixture

Light fixture installation has commenced at the adult collection area.

Floor grille

View of the adult collection area. Floor grille installations at the perimeter are ongoing.

washroom

Prep work is almost complete for tile installation in the washrooms.

 

 

Civic Centre Resource Library – Feb. 2

Bookmark and Share

This week at the Civic Centre Resource Library, workers are continuing to install miscellaneous framing around the glazing on the east and south face. Framing work is still ongoing at the main entrance at the south side, and the framing of the vestibule is progressing with drywall installation at the ceiling.Painters are on site and are spraying the ceiling at the children’s zone, moving west towards the proposed computer area. Installation of the elevator is ongoing now that the electrical work is complete.

1

View of east elevation at the main lobby. Framing is ongoing at stairwell A.

2

Ceiling spray painting has commenced over the children's area.

3

Drywall mudding has been completed at the multi-purpose training room and the teen zone.

4

The elevator is in place and final connections are ongoing.

Drop Ceiling

Drop ceiling (T-bar) installation has commenced at the 2nd floor northeast corner.

Civic Centre Resource Library – Jan. 20

Bookmark and Share

The cold weather has not not stopped the Civic Centre Resource Library from moving forward. As of this week, workers continue to install composite panels on the east and south sides. Framing work is ongoing at the main entrance. Interior steel stud work has progressed in all areas and is ongoing at the second level mezzanine. Installation of the elevator is ongoing now that the electrical work is complete. Painters are on site to commence work.

View of the southeast elevation.

2

View of the main entrance.

3

Framing and drywall is almost complete at the multi-purpose training room.

5

View of the program room.

6

Primer painting to commence at the adult collection area.

 

Civic Centre Resource Library – Dec. 23

Bookmark and Share

Things are moving along quickly at the Civic Centre Resource Library this week. Workers continue to install composite panels on the east side. Framing work is still ongoing at the main entrance at the south. Glazing installation continues around the exterior perimeter (east and south elevations). Interior steel stud work has progressed in all areas and is ongoing at the second level mezzanine and stairwell areas. Drywall installation continues throughout the first floor along with mudding and taping. Temporary plywood has been installed to enclose the building until exterior glazing and panelling can be completed in January.

1

View of main entrance.

2

View of main lobby.

3

View of computer area.

View of interactive family area.

View of maker space & teen area.

View of maker space & teen area.

 

 

Civic Centre Resource Library – Dec. 9

Bookmark and Share

This week at the Civic Centre Resource Library, workers continue to install composite panels on the south side. Framing work is still ongoing at the main entrance. Glazing installation continues to move along around the exterior perimeter. Electrical work is underway for connections to the elevator. Gas feed to the building is in place and heaters are on site to be installed. In addition, trees for the courtyard have been planted.

Concrete work is complete at the west elevation.

Drywall installation is in progress at the adult collections area.

Front entrance frame work is ongoing.

Trees have been planted in the courtyard.

Civic Centre Resource Library – Nov. 30

Bookmark and Share

Things are moving quickly at the Civic Centre Resource Library. Here is an update on what is happening at the construction site.

  • Exterior insulation installation is taking place around the north, west and south elevations.
  • Workers continue to install paneling on the south side.
  • Framing work is still ongoing at the main entrance at the south side.
  • Glazing installation continues around the exterior perimeter at the east elevation.
  • Hardscaping activities continue around the building.
  • Sidewalk continues to be poured around the perimeter as well as the pads at the main entrance.
  • Drywall installation continues throughout the first and second floor.
1

Concrete work is ongoing around the perimeter.

2

Hardscaping work is progressing at the south side.

3

Drywall work is almost complete.

4

Lounge area and study hall space in progress.

 

Civic Centre Resource Library – Nov. 12

Bookmark and Share

Things are moving quickly at the Civic Centre Library. Here is a quick update on what is happening as of this week.

  • Exterior insulation installation is complete at the south side of the building.
  • Framing and welding at the main entrance is ongoing.
  • Glazing installation continues around the exterior perimeter at the east elevation.
  • Composite panel installation is progressing at the north side and around the Reading Garden.
  • Sidewalks are 50% poured at the north side and curb work is progressing at the east and north sides.
  • Interior steel stud work has progressed in all areas.
  • Drywall installation continues throughout the first and second floors.
Floor pLan

Floor Plan - 1st floor.

Floor Plan 2

Floor Plan - 2nd floor.

View of east elevation.

Sidewalk is 50% poured at the east elevation.

Hardscape work has progressed at the east side.

Steel welding and aluminum welding at the main entrance is ongoing.

Glazing installation is complete at the Reading Garden with the exception of the exits.

View of the second floor patio. Roof work is complete and finish work is to be scheduled.

Vaughan Public Library Board announces the official name of the new resource library

Bookmark and Share

The Vaughan Public Library Board is pleased to announce VPL’s third resource library will be officially named the Civic Centre Resource Library. The name was selected from an extensive list of suggestions received from hundreds of Vaughan citizens, through a survey, and additional names of historical significance amassed with input from City of Vaughan Archives staff. VPL thanks everyone who provided their valuable input in naming this library.

Construction of the Civic Centre Resource Library is progressing well. As of this week, the exterior insulation installation is ongoing at the south side of the building perimeter with roxul insulation. Glazing installation continues around the exterior perimeter. Another shipment of glazing has been received and installation along the south and east walls are to commence. Hardscaping along the south, west and north sides are ongoing. Mechanical and electrical rough-ins are complete. Connections of exhaust fans and fixture rough-ins are underway. Interior steel stud work has progressed in all areas. Drywall installation continues throughout the first and second floor.

View of the south elevation.

Framing and insulation work is ongoing at the market place.

View of the main entrance at the south.

Walls at the Digital Media Lab are taking form.

Walls at the Digital Media Lab are taking form.

View of the 2nd floor patio.

 

Civic Centre Resource Library – Oct. 9

Bookmark and Share

Glazing installation continues around the exterior perimeter. The north and west elevations as well as the reading garden are approximately 90% closed in. Hardscaping activities along the south, west and north continues.  Grading is almost complete along the north. Mechanical and electrical rough-ins are complete. Interior steel stud work has progressed in all areas. Drywall installation is underway at the mezzanine and second floor areas.

glazing

Glazing installation is almost complete at the reading garden.

market place

View of the Market Place with second floor balcony above.

Music Room

Music Room walls are taking form.

Stairs

Drywall mudding and taping has commenced at stair B.

Program room

Insulation and boarding is progressing at the program rooms and kitchenette.

offices

2nd floor administration area is starting to take form.