VMC and VMC Express are experiencing significant progress this month. The curtain wall glass installation in both library spaces is now complete; this includes full installation of the library’s entrance sliding doors, glass walls and all remaining glass doors. Fabrication of the library’s service desk is now also complete, and the installation is expected to take place in the next couple of weeks. Millwork of the VMC Express is currently in fabrication, and the support structure should be complete shortly.

Completed installation of the library entrance and interior glass wall
Glass wall installation complete in manager’s office and staff workroom
Glass wall and door installation complete in Quiet Study area
Glass wall and door installation complete in Quiet Study area
Electrical installation of feature lighting in Children’s Area is now complete

Maple Library Renovation Project Update

Bookmark and Share

Construction on Maple Public Library continues to experience significant progress. The work on wall framing, duct installation, taping, and light fixtures is nearly complete. Installation of the leaf fixture is still in progress and starting to take shape. Work on the Reading Garden has begun as well as the Staff Kitchen and Staff Workroom.

Leaf Installation in Reading Lounge
Leaf stem installation
Leaf installation in Quiet Study Area
Library entrance area
Staff Workroom
Staff Kitchen
Work on pillars has begun
Reading Garden entrance
Reading Garden area
Reading garden – trellis structure preparation work in progress.
Library light installation in progress
Installation of new windows in children’s area is now complete