We continue to see progress at VMC Library and VMC Express. Support structure for VMC Express millwork is currently being installed, while millwork for VMC will commence next month. We’ve received the remaining furniture; staff work furniture, manager’s office set and study tables are now in place. Library collections and equipment are scheduled to be received in early February.
Monthly Archives: December 2021
Maple Library Renovation Project Update
Construction activities at the Maple Library Community Centre are progressing. Activities include ceiling installation, wall finish and painting, glazing installation in the quiet study area, carpet, decorative film installation, and many activities associated with the outdoor reading garden. In the next couple of weeks, construction will include the installation of an outstanding ceiling grid, ceiling tiles, baffle installation, and glass installation in the quiet study area. Front foyer work will commence with replacing floor tiles and the leadership structure installation.