Glazing installation continues around the exterior perimeter. The north and west elevations as well as the reading garden are approximately 90% closed in. Hardscaping activities along the south, west and north continues. Grading is almost complete along the north. Mechanical and electrical rough-ins are complete. Interior steel stud work has progressed in all areas. Drywall installation is underway at the mezzanine and second floor areas.
Civic Centre Resource Library – Oct. 9