Project Update – VMC Library & VMC Express

Bookmark and Share

We continue to see progress at VMC Library and VMC Express. In the library area, field carpet installation is now complete in preparation for the carpet tile installation. This activity is being coordinated in tandem with library shelving delivery and set up. Some glazing installation and millwork activity continues to progress as well.

 

Lobby Area. View onto 2nd level; quiet Study Area and future Green Wall.

 

Staircase to second-floor library and third-level Recreation Space.

 

Millwork installation in Children’s Area.

 

Field carpet installation complete. Carpet tile installation to follow.

 

View onto lobby from Library’s Quiet Study Area.

 

Teaching Kitchen