Bookmark and Share

Civic Centre Resource Library – Nov. 30

Things are moving quickly at the Civic Centre Resource Library. Here is an update on what is happening at the construction site.

  • Exterior insulation installation is taking place around the north, west and south elevations.
  • Workers continue to install paneling on the south side.
  • Framing work is still ongoing at the main entrance at the south side.
  • Glazing installation continues around the exterior perimeter at the east elevation.
  • Hardscaping activities continue around the building.
  • Sidewalk continues to be poured around the perimeter as well as the pads at the main entrance.
  • Drywall installation continues throughout the first and second floor.
1

Concrete work is ongoing around the perimeter.

2

Hardscaping work is progressing at the south side.

3

Drywall work is almost complete.

4

Lounge area and study hall space in progress.

 

Comments are closed.