Pleasant Ridge Library Opens Dec. 20

Bookmark and Share

Pleasant Ridge Library is opening on December 20 at 10 a.m. We invite everyone to come and see this beautiful new library and check out all the great services and programs the library offers. See you there!

PL

Kleinburg Library Update – Nov. 20

Bookmark and Share

Kleinburg library is shaping up, things are looking good and the library is expected to re-open on Dec. 8 at 1 p.m.

KL1

The front of the library is starting to reflect the final look.

KL2

The reading garden is nearing completion.

KL2

the new rear entrance to the lower level is currently being worked on.

 

Civic Centre Resource Library – Nov. 19 update

Bookmark and Share

There’s lots happening at the Civic Centre Resource Library construction site this week! Check out some new photo updates below.

CCRL

Formwork continues along the east wall at the north corner.

CCRL

Elevator pit has been poured and formwork has been removed.

CCRL

Reading garden perimeter foundations appear to be complete and backfilled.

CCRL

Interior trenching for underground services has commenced.

CCRL

Stair B foundation is complete.

CCRL

Foundation waterproofing and insulation is ongoing.

Civic Centre Resource Library Update – Nov. 12

Bookmark and Share

Things are progressing at the Civic Centre Resource Library this week. Workers continue to work on the formwork and the foundations. The waterproofing of the foundations has commenced. The rebar installation has been completed. Forms are ready for concrete on the right and the concrete pour has been completed on the left side.

CCRL

Formwork and foundations are ongoing.

CCRL

Waterproofing of the foundations has commenced.

CCRL

Rebar installation has been completed.

CCRL

Piers are completed and formwork has been removed.

CCRL

Forms are ready for concrete on the right and concrete pour is complete on the left.

CCRL

General view of the site.

 

Kleinburg Library Update – Nov. 7

Bookmark and Share

Things are progressing at Kleinburg Library. The second floor duct work is being finished,  the east side windows have been installed, and the retainer wall for the new basement entrance has also been completed.

 ductwork

The second floor duct work is being completed.

walkway

Access walkway from front of library to rear basement entrance.

Windows

East side windows have been installed.

Retainer wall

Retainer wall is being completed for the new basement entrance.

 

Civic Centre Resource Library Update – November 5

Bookmark and Share

Construction work on the Civic Centre Resource Library began in September.  Excavation of the site is now completed and the site has been elevated and leveled to the level of the street.

Workers have now finished the footing installation, and the installation of foundation wall forms and backfilling of the building envelope continues.

Here are a few photo updates of the construction site.

civic1civic2civic3civic4civic5civic6