PROGRESS UPDATE

Vaughan Metropolitan Centre (VMC) Library and VMC Library Express are coming to you very soon! 90% of the drywall work has been completed in both library areas and most walls and ceilings have been painted. The lighting installation is also 50% complete with the large continuous fixtures installed at the Children’s area and in the main library area.

In the next few weeks, ceiling and interior glazing wall installation are scheduled to begin. The interior and exterior signage installation are also in the works.

Substantial completion continues to be set for mid-July. Soft opening is targeted for August and the official opening end of September.

First library lights have been installed. Ceiling preparation for the wood ceiling installation has been completed.