Vellore Village Library: March 6 Update

Construction activities continue at the site of the new library. Glazing installation is nearly completed as insulation, drywalling and taping work continues. Ceiling framing and hangers are well underway and preparation for ceiling work has started.

Activities scheduled for the next two weeks include framing of the structural soffit, ceiling hangers installation, completion of bulkhead framing, tile work and IT room set-up to power equipment.

Drywalling and taping progressing well

Drywalling and taping are progressing well.

Ceiling installation preparation

Preparation for ceiling installation.

Tiling in washroom area

Tiling is underway in the washroom area.

Drywalling in children's area

Drywalling ongoing in the children’s area.

Study room insulation and drywalling

Insulation and drywalling activities in the study room.

Electrical panels installed in IT room

Electrical panels have been installed in the IT room.

Decorative roofing detail ongoing

Decorative roofing detail work is ongoing.