Lots has happened at the Civic Centre Resource Library this week. The slab pour took place on the second level. Scaffolding and railings are secured in place. Metal decking has been completed over both levels. Metal stair construction has commenced, stair B and C are being fastened in place. Mechanical and electrical rough-in and stub ups are ongoing and they will be progressing through to the second floor in the next two weeks. Mechanical is continuing to install hangers for duct installation.

Trimmer angle has progressed around the second floor. Scaffolding is also in place for work on the second floor.