Since the groundbreaking on September 19th, crews have excavated and disposed of the existing asphalt and base layer, created a new trench for drainage, installed electrical conduits for a new pole light and EV charging stations, and installed new concrete curbs. In addition, the creation of the new Multi-Use Path is well underway.

The remaining activities will include placement and compaction of subgrade surfacing, new asphalt and line painting, landscape work, and installation of furniture and fixtures.