Most of the walls, columns and ceiling are framed in and are approximately 65% complete with drywall. Mudding and taping will follow shortly. Some structural remediation from the base contract phase is also underway. Stair installation from the main floor to the second floor is now taking place. The library space is feeling great with wonderful views and is bright with light entering the space throughout the day. Anticipated substantial completion continues to be set for Summer 2020.