Project Update – Vaughan Metropolitan Centre Library

PROGRESS OF CONSTRUCTION WORK

The Vaughan Metropolitan Centre Library (VMC) and Storefront Library construction fit-out phase continues with great progress in the Price Waterhouse Cooper (PwC) office building. Wall studs and rough in work for plumbing is ongoing throughout both library spaces, and electrical work is also scheduled concurrently. Graphics and signage processes have started and architects are working with a lighting consultant investigating options for the colour changing light strip for the second-floor library. Landscaping work is well underway throughout the site with a substantial completion targeted for Summer 2020 followed by the opening of the full facility.

View from south, next to transit terminal, showcasing the gold band around library

Landscaping work ongoing

Landscaping progress

 

 

 

 

 

Interior fit-out work progress

Framing of staff workroom

Framing of quiet study room

 