Project Update – VMC Library & VMC Express

Bookmark and Share

We continue to see progress on both VMC Library and VMC Express. Slatwall, glazing and painting are amongst the many things that have happened in the last several weeks. Check out the images below to catch a glimpse at some of the progress.

Slatwall installation in the main lobby below Library
Glazing installation on Library’s Quiet Study Room
Glazing installed in VMC Express
Painting activities ongoing in VMC Express

Project Update – VMC Library & VMC Express

Bookmark and Share

Both the VMC Library and Library Express are progressing. To date, VPL has received a number of deliveries including library shelving, merchandising furniture, study chairs and some soft chairs. Check out the images below to catch a glimpse at some of the progress.

Workers installing transition rails in preparation of glass wall that will be installed in the library’s Marketplace
Glass installation in the manager’s office
Workroom furniture partially installed
Library shelving installed and merchandising furniture received
Quiet Study room being painted with a final coat of paint.
Study chairs have been received
Marketplace soft seating chairs have also been received
Counter height study tables partially installed. 

Project Update – VMC Library & VMC Express

Bookmark and Share

The VMC Library and VMC Express are currently under construction in the Pricewaterhouse Coopers office building in the city’s new downtown area. Check out the images below to catch a glimpse at some of the progress.

Library shelving delivery arrives from Nova Scotia!
The crew are offloading
Installation of library’s sliding entrance doors has been completed
Stairwell glazing has been completed
Shelving installation begins
Magazine and merchandising furniture
Installation of shelving in the children’s area
Staff workroom and completed glazing in the manager’s office
VMC Express.  Flooring work is complete and framing in place awaiting glass installation
View from inside the VMC Express

Project Update – VMC Library & VMC Express

Bookmark and Share

We continue to see progress at VMC Library and VMC Express. In the library area, field carpet installation is now complete in preparation for the carpet tile installation. This activity is being coordinated in tandem with library shelving delivery and set up. Some glazing installation and millwork activity continues to progress as well.

 

Lobby Area. View onto 2nd level; quiet Study Area and future Green Wall.

 

Staircase to second-floor library and third-level Recreation Space.

 

Millwork installation in Children’s Area.

 

Field carpet installation complete. Carpet tile installation to follow.

 

View onto lobby from Library’s Quiet Study Area.

 

Teaching Kitchen

Project Update – VMC Library & VMC Express

Bookmark and Share

Activities in both library spaces continue to progress. The non-carpeted areas in both libraries have now been installed. Carpet installation is expected to take place in the next week. Installation of lightbox fixture as well as all fixed millwork furniture including counter height study tables and integrated millwork benching is ongoing. Installation of glazing has now also begun in the second-level library space.

View from YMCA’s Yoga Studio to lobby and second-level library.

 

Lightbox installation in progress.

 

Quite Study Room.

 

Staff Workroom. Hard surface flooring has been installed and is being protected.

 

Millwork Bench Installation in Children’s Area.

 

Counter height study tables overlooking Transit Square.

 

City of Vaughan Community Kitchen to be programmed by VPL.

 

City of Vaughan Community Kitchen to be programmed by VPL.

 

Project Update – VMC Library & VMC Express

Bookmark and Share

The VMC Library and VMC Express construction activities are progressing as per the project schedule.

The 9000 sq ft library will be located on the second floor of the office building while the 400sq ft VMC Express will be located below the library directly at the street level.

Lightbox samples that will be installed on the north wall of the VMC Library.

 

Glazing work continues and glass partitions and glass walls are being installed. Carpet installation has begun, and the staged approach is anticipated to take place over the course of the next few months. Lightboxes will also be installed on the north wall of the VMC Library. Lightboxes help maximize visibility, adds vibrancy to space, and are cost-efficient and energy-saving.

Rendering of Lightboxes planned for VMC Library.

Project Update – VMC Library & VMC Express

Bookmark and Share

The VMC Library and VMC Express are currently under construction in the Pricewaterhouse Coopers office building in the city’s new downtown area.

The 9000 sq ft library will be located on the second floor of the office building while the 400 sq ft VMC Express will be located below the library directly at the street level.

External view of VMC Express

Internal view into VMC Express

Eastwards view of VMC Library. View from Children’s Area towards the Marketplace.

Completed wood ceiling and electrical work in Children’s Area.

Ceiling work in the remaining library space.

Main entrance door frame installation completed.

Hallway view depicting VMC Express on the main floor, VMC Library on the second floor, and CoV Recreational Space on the third floor.

Project Update – VMC Library & VMC Express

Bookmark and Share

PROGRESS UPDATE

Work at the VMC Library and VMC Express is progressing well as contractors continue to work in accordance with the capacity limits. Construction timeline is on track per revised post-Covid schedule, with the exception of glass related items that include glazed partitions and glass doors. This is due to an industry-wide delay currently being experienced by most glass manufactures. We are anticipating a substantial completion target for January 2021.

VMC Express

VMC Express

Staircase view from the Marketplace in the VMC Library

Wood ceiling installation began in the Children’s Area

View from individual study area over the open area of Balzac’s Coffe

Stunning view into the Balzac’s Coffe from Library

Main floor lobby finishes include completed terrazzo flooring, finished walls

Main floor lobby wood panel installation currently still in progress

Project Update – VMC Library & VMC Express

Bookmark and Share

PROGRESS UPDATE

On April 3, 2020, construction came to a halt at Vaughan Metropolitan Centre (VMC) Library and VMC Express as per the Province’s directive in the fight of COVID-19. Since May 18, 2020, construction activities have resumed and contractors are back on site working in accordance with the required guidelines. Anticipated opening of the new facility is targeted for Winter 2021.

Credits: www.myvmc.ca

Library view east towards market place

Staircase to the 3rd floor visible from the children’s area.

Children’s area facing north

What’s happening at Vaughan Metropolitan Centre Library & VMC Library Express?

Bookmark and Share

PROGRESS UPDATE

Vaughan Metropolitan Centre (VMC) Library and VMC Library Express are coming to you very soon! 90% of the drywall work has been completed in both library areas and most walls and ceilings have been painted. The lighting installation is also 50% complete with the large continuous fixtures installed at the Children’s area and in the main library area.

In the next few weeks, ceiling and interior glazing wall installation are scheduled to begin. The interior and exterior signage installation are also in the works.

Substantial completion continues to be set for mid-July. Soft opening is targeted for August and the official opening end of September.

First library lights have been installed. Ceiling preparation for the wood ceiling installation has been completed.

View from Children’s Area east towards the Marketplace

Stairwell from main lobby to second level library and third level CoV’s space.

Quite Study Area visible from downstairs lobby