We continue to see progress on both VMC Library and VMC Express. Slatwall, glazing and painting are amongst the many things that have happened in the last several weeks. Check out the images below to catch a glimpse at some of the progress.
Project Update – VMC Library & VMC Express
Both the VMC Library and Library Express are progressing. To date, VPL has received a number of deliveries including library shelving, merchandising furniture, study chairs and some soft chairs. Check out the images below to catch a glimpse at some of the progress.
Project Update – VMC Library & VMC Express
The VMC Library and VMC Express are currently under construction in the Pricewaterhouse Coopers office building in the city’s new downtown area. Check out the images below to catch a glimpse at some of the progress.
Project Update – VMC Library & VMC Express
We continue to see progress at VMC Library and VMC Express. In the library area, field carpet installation is now complete in preparation for the carpet tile installation. This activity is being coordinated in tandem with library shelving delivery and set up. Some glazing installation and millwork activity continues to progress as well.
Project Update – VMC Library & VMC Express
Activities in both library spaces continue to progress. The non-carpeted areas in both libraries have now been installed. Carpet installation is expected to take place in the next week. Installation of lightbox fixture as well as all fixed millwork furniture including counter height study tables and integrated millwork benching is ongoing. Installation of glazing has now also begun in the second-level library space.
Project Update – VMC Library & VMC Express
The VMC Library and VMC Express construction activities are progressing as per the project schedule.
The 9000 sq ft library will be located on the second floor of the office building while the 400sq ft VMC Express will be located below the library directly at the street level.
Glazing work continues and glass partitions and glass walls are being installed. Carpet installation has begun, and the staged approach is anticipated to take place over the course of the next few months. Lightboxes will also be installed on the north wall of the VMC Library. Lightboxes help maximize visibility, adds vibrancy to space, and are cost-efficient and energy-saving.
Project Update – VMC Library & VMC Express
The VMC Library and VMC Express are currently under construction in the Pricewaterhouse Coopers office building in the city’s new downtown area.
The 9000 sq ft library will be located on the second floor of the office building while the 400 sq ft VMC Express will be located below the library directly at the street level.
Project Update – VMC Library & VMC Express
PROGRESS UPDATE
Work at the VMC Library and VMC Express is progressing well as contractors continue to work in accordance with the capacity limits. Construction timeline is on track per revised post-Covid schedule, with the exception of glass related items that include glazed partitions and glass doors. This is due to an industry-wide delay currently being experienced by most glass manufactures. We are anticipating a substantial completion target for January 2021.
Project Update – VMC Library & VMC Express
PROGRESS UPDATE
On April 3, 2020, construction came to a halt at Vaughan Metropolitan Centre (VMC) Library and VMC Express as per the Province’s directive in the fight of COVID-19. Since May 18, 2020, construction activities have resumed and contractors are back on site working in accordance with the required guidelines. Anticipated opening of the new facility is targeted for Winter 2021.
What’s happening at Vaughan Metropolitan Centre Library & VMC Library Express?
PROGRESS UPDATE
Vaughan Metropolitan Centre (VMC) Library and VMC Library Express are coming to you very soon! 90% of the drywall work has been completed in both library areas and most walls and ceilings have been painted. The lighting installation is also 50% complete with the large continuous fixtures installed at the Children’s area and in the main library area.
In the next few weeks, ceiling and interior glazing wall installation are scheduled to begin. The interior and exterior signage installation are also in the works.
Substantial completion continues to be set for mid-July. Soft opening is targeted for August and the official opening end of September.