Members of the Vaughan Public Library (VPL) Board, Deputy Mayor, Members of Council and VPL staff attended a topping off ceremony for the new Pleasant Ridge Library (located at 300 Pleasant Ridge Avenue) on Friday, June 6 to celebrate the topping off of the library structure and to welcome the next phase of construction. As part of the ceremony, attendees signed one of the structure’s steel beams.

Since the construction began in February, things have progressed quickly. The steel structure of the building is almost complete and the new library is expected to open by year end.

group shot

(From L to R): Ward 1 Councillor and VPL Board Trustee Marilyn Iafrate, VPL Board Trustee Suri Rosen, VPL CEO Margie Singleton, Deputy Mayor, Regional Councillor and VPL Board Trustee Gino Rosati, VPL Board Chair Michael McKenzie, President of Maystar General Contractors Joe Maio, Regional Councillor and VPL Board Trustee Michael Di Biase, Ward 4 Councillor Sandra Yeung Racco, VPL Board Trustee Marie Chiaromonte, VPL Board Trustee Lorraine de Boer and Vice-Chair of VPL Board Devender Sandhu attended the Pleasant Ridge Library topping off ceremony on Friday, June 6

photo 4

(From L to R): CBRE Senior Project Manager Anthony Boland, City of Vaughan Director of Building & Facilities Michael Shatil, Maystar General Contractors' Project Managers Frank Riga and Luciano Di Giuiseppe, VPL Director of Planning and Communications Terri Watman, Maystar General Contractors' General Superintendent Jim Egnatis and Site Superintendent Michael Murphy

photo 4

(From L to R): VPL CEO Margie Singleton, President of former Thornhill Woods Community Association Maya Goldenberg and Ward 4 Councillor Sandra Yeung Racco

photo 5

(From L to R): VPL Board Trustee Marie Chiaromonte, VPL Board Trustee Suri Rosen, Ward 4 Councillor Sandra Yeung Racco, VPL Board Chair Michael McKenzie, President of Maystar General Contractors Joe Maio, VPL CEO Margie Singleton, Regional Councillor and VPL Board Trustee Michael Di Biase, Ward 1 Councillor and VPL Board Trustee Marilyn Iafrate, Deputy Mayor, Regional Councillor and VPL Board Trustee Gino Rosati, VPL Board Trustee Lorraine de Boer and Vice-Chair of VPL Board Devender Sandhu signing the beam

photo 6

(From L to R): VPL Board Chair Michael McKenzie, VPL CEO Margie Singleton and Deputy Mayor, Regional Councillor and VPL Board Trustee Gino Rosati signing the beam

photo 8

(From L to R): CBRE Senior Project Manager Frank Boland, Maystar General Contractors' Project Managers Frank Riga and Luciano Di Giuiseppe, VPL Director of Planning and Communications Terri Watman, Maystar General Contractors' General Superintendent Jim Egnatis and Site Superintendent Michael Murphy

(From L to R): Ward 4 Councillor Sandra Yeung Racco, President of former Thornhill Woods Community Assocation Maya Goldenberg and VPL CEO Margie Singleton signing the beam

photo 9

Master of Ceremonies – VPL Board Chair Michael McKenzie

photo 11

Deputy Mayor, Regional Councillor and VPL Board Trustee Gino Rosati

photo 12

Ward 4 Councillor Sandra Yeung Racco

Pleasant Ridge Library – more photo updates

Bookmark and Share

Check out a few more great shots of the erection of structural steel at Pleasant Ridge. Bolting is being finalized and steel connections are being linked.

PLRMay30PLRMay30PLRMay30PLRMay30PLRMay30

Pleasant Ridge Library Update – May 29

Bookmark and Share

The structural steel is going up quickly at Pleasant Ridge Library.

As of May 23

structural steelstructural steelAs of May 28

structural steel

 

Pleasant Ridge Library Update – May 21

Bookmark and Share

Last week, trucks were at Pleasant Ridge Library getting ready to pour the slab on grade. As of May 21, the concrete foundation has been laid, workers were installing the poles with the help of a big crane. A steel outline of the library was already up by the end of the day!

May 16

Pleasant Ridge Library

Trucks getting reading to pour slab on grade

Pleasant Ridge Library

May 21

PLRmay21

Concrete foundation has been laid

PRLmay21

PRLmay21

Installing the poles with the help of a big crane

PRLmay21

Workers installing the poles

May 21

Steel outline of the library

Pleasant Ridge Library Update – May 15

Bookmark and Share

Construction continues at Pleasant Ridge this week. The granular fill is in progress. Trenching for electrical rough-in and underground electrical rough-in are done. The electrical underground conduit has also been installed.

Pleasant Ridge Library - May 15

Granular fill in progress

Pleasant Ridge Library - May 15

Granular fill in progress

Pleasant Ridge Library - May 15

Trenching for electrical rough-in

Pleasant Ridge Library - May 15

Underground electrical rough-in

Pleasant Ridge Library - May 15

Electrical underground conduit being installed

Pleasant Ridge Update – May 1

Bookmark and Share

Construction continues at Pleasant Ridge Library.

Pleasant Ridge Library

Underground plumbing rough-in

Pleasant Ridge Library

Tie in to existing sanitary line

Pleasant Ridge Library

Building foundation

Pleasant Ridge Library

Demolition of existing building link canopy

Pleasant Ridge Library

Link foundation

Pleasant Ridge Library Update – April 17

Bookmark and Share

Things are moving along smoothly at Pleasant Ridge this week.

Pleasant Ridge Library Construction

The foundation has been completed! The backfilling of dirt around the wall has also been completed.

Pleasant Ridge Library Construction

The existing canopy has been removed.

Things Progress at Pleasant Ridge Library

Bookmark and Share

Construction continues this week at Pleasant Ridge Library.

pleasant ridge libraryPleasant Ridge Library

 

 

Pleasant Ridge Library Project Update

Bookmark and Share

Construction continues on the new library. Photos below show the backhoe taking off the overhang from the community centre exit and the footings and foundation work that started last week.

 

Construction Has Begun On Pleasant Ridge Library!

Bookmark and Share

Great news! Construction has begun on Pleasant Ridge Library! The hoarding fence is up, the construction trailer is on site and the big digging machines are at work.

The new library will be located north of the existing North Thornhill Community Centre building in an area bounded by the existing tennis courts to the west, existing parking lot to the north and east, and the existing community centre building to the south.

We will keep you up to date on the progress.