As of this week, the window frames have been delivered on site, the roofing membrane installation is in progress, the window openings are being tarped and more are still happening. Here is a quick photo update.
Pleasant Ridge Update – Sept. 5

If you pass by Pleasant Ridge Library this week, you will see that a lot of masonry work has been done already. Work on the air barrier and the roofing has begun!
Construction continues at Pleasant Ridge this week and things are moving quickly.
Major activities including duct work installation, electrical rough-in, and the installation of sprinkler piping and exterior cladding substrate continue.
Construction on the Pleasant Ridge Library continues to progress smoothly. The installation of exterior cladding substrate has started. Work continues on the installation of the duct work, electrical rough-in, sprinkler piping and radiant floor lines.
The site signage is up at Pleasant Ridge Library. The installation for the duct work, electric rough-in, sprinkler main are in progress. The roof top units have already been installed.
The parameter wall structure, drywall steel installation are progressing at Pleasant Ridge Library. The roof curb material arrived for installation and drywall steel studs are being installed.