Project Update – VMC Library & VMC Express

PROGRESS UPDATE

Work at the VMC Library and VMC Express is progressing well as contractors continue to work in accordance with the capacity limits. Construction timeline is on track per revised post-Covid schedule, with the exception of glass related items that include glazed partitions and glass doors. This is due to an industry-wide delay currently being experienced by most glass manufactures. We are anticipating a substantial completion target for January 2021.

VMC Express

VMC Express

Staircase view from the Marketplace in the VMC Library

Wood ceiling installation began in the Children’s Area

View from individual study area over the open area of Balzac’s Coffe

Stunning view into the Balzac’s Coffe from Library

Main floor lobby finishes include completed terrazzo flooring, finished walls

Main floor lobby wood panel installation currently still in progress