The holidays are approaching, but work at the Civic Centre Resource Library is not slowing down. Concrete work for the foundations has been completed; piers and cloumn bases have been covered with straw, plastic and gravel for weather and moisture protection; reading garden bench concrete has cured and formwork has been removed and more. See below for some great photo updates!
Concrete work for the foundations has been completed. Final installation for insulation was taking place at the northeast corner.
Piers & column bases have been covered with straw, plastic and gravel for weather and moisture protection.
Reading garden bench concrete has cured and formwork has been removed.
Underground services appear to be complete and stubbed up above grade for further connections.
Elevator pit has been fenced off.
North perimeter foundations view.
Grading has commenced on the proposed interior around the reading garden.
Gravel is on site for slab on grade preparation.