Civic Centre Resource Library – Sept. 18

This week at the Civic Centre Resource Library, exterior sheathing installation continues to progress around the building perimeter and work is ongoing at the south side. Glazing installation has commenced and panels are being installed around the reading garden as well as the north elevation. Hardscaping activities started along the south with the drilling and installation of sonotubes for piers.

1

Exterior commenced at the south elevation.

2

Glazing installation commenced at the north elevation.

3

Hardscaping work has commenced. Workers are drilling piles to install sonotubes.

4

Interior insulation has commenced at the adult collection.

6

Glazing installation at the Reading Garden is ongoing.

 

 