Bookmark and Share

Civic Centre Resource Library – April 10

As of this week, the primary structural steel appears to be complete. Installation of the secondary steel such as trim edges is ongoing. Metal decking installation is complete on the first level, and is approximately 60% complete on the second level. Mechanical and electrical rough-in as well as connection welding continue to progress.

View of the west from the courtyard.

Metal decking work continues on the second level.

Electrical rough-in has progressed at maker space & music room.

Secondary steel-trim edges are being installed.

Structural tie-ins are ongoing.

 