Bookmark and Share

Civic Centre Resource Library – April 3

As of this week, the primary structural steel is almost complete. Installation of secondary steel such as trim edges is ongoing. Connection welding continues. Metal decking over the first floor is in place and has started on the second floor. Mechanical and electrical rough-in has begun. Installation of rain water leaders at the collaboration space is underway. Conduit runs are being installed at the maker space and music room areas.

Apr.3

Steel work is ongoing.

april 2

Decking work has commenced at second floor.

april3

Grading is ongoing in preparation for slab on grade.

april3

Electrical rough-in commenced above ground at maker space & music room.

april3

Roof joist connections are ongoing.

 

 

Comments are closed.