Civic Centre Resource Library Update – Nov. 12

Things are progressing at the Civic Centre Resource Library this week. Workers continue to work on the formwork and the foundations. The waterproofing of the foundations has commenced. The rebar installation has been completed. Forms are ready for concrete on the right and the concrete pour has been completed on the left side.

CCRL

Formwork and foundations are ongoing.

CCRL

Waterproofing of the foundations has commenced.

CCRL

Rebar installation has been completed.

CCRL

Piers are completed and formwork has been removed.

CCRL

Forms are ready for concrete on the right and concrete pour is complete on the left.

CCRL

General view of the site.

 