Pleasant Ridge Update – Sept. 11

As of this week, the window frames have been installed and drywall installation is in progress. The directional boring for the electric conduit has been completed and the electric room is ready for floor cutting.

window

Window frames being installed.

Window frames installed.

drywall

Drywall installation started in the electric room.

Drywall

Drywall installation continues.

directional boring

Directional boring for electrical conduit has been completed.

 

electric

The electric room has been covered up to prepare for floor cutting.

 