Pleasant Ridge Library Update – June 30

The site signage is up at Pleasant Ridge Library. The installation for the duct work, electric rough-in, sprinkler main are in progress. The roof top units have already been installed.

june 27

Site signage is up

june27

Installing the duct work

june 27

Installing the electric rough-in

june 27

Installing the sprinkler main

june 27

Opening the roof for roof top units

june27

Roof top units installed