Grass and Plants at Pleasant Ridge Library

Bookmark and Share

Pleasant Ridge Library is looking better than ever with new grass and plants put in outside of the library. Check out some great new photos below.

PL2

Woodbridge Library Closed for Renovations May 26 – 29

Bookmark and Share

Woodbridge Library will be closed for renovation starting on Tuesday, May 26 and will re-open on Saturday, May 30 at 10 a.m. During this time, customers may return library materials at any location of Vaughan Public Libraries (VPL) or renew them online at www.vaughanpl.info. Customers may deactivate holds online or pick them up at Pierre Berton Resource Library.  For more assistance deactivating holds, please ask a staff at the Service Desk.  We apologize for any inconveniences.

Kleinburg Library Invites You to Its Re-Opening Celebration

Bookmark and Share

Kleinburg Library invites you to its Re-opening Celebration on May 29, from 11 a.m. to 1:30 p.m. A special children’s storytime will be held at 11 a.m. followed by official remarks by the Hon. Maurizio Bevilacqua P.C., Mayor of Vaughan.  Everyone is welcome to discover the newly renovated library and enjoy light refreshments. See you there!

Civic Centre Resource Library – May 8

Bookmark and Share

Lots has happened at the Civic Centre Resource Library this week. The slab pour took place on the second level. Scaffolding and railings are secured in place. Metal decking has been completed over both levels. Metal stair construction has commenced, stair B and C are being fastened in place. Mechanical and electrical rough-in and stub ups are ongoing and they will be progressing through to the second floor in the next two weeks. Mechanical is continuing to install hangers for duct installation.

CCRL

Trimmer angle has progressed around the second floor. Scaffolding is also in place for work on the second floor.

CCRL

Slab has been poured on the second floor.

CCRL

Safety rails are now in place around the second floor for work to take place.

CCRL

Stair C is in place adjacent to the washroom and maker space room.

CCRL 5

Stair B connections are ongoing at the northeast stairwell.

CCRL 6

Electrical service to the second floor is ongoing.

 

Civic Centre Resource Library – May 1

Bookmark and Share

Metal decking over is approximately 95% complete over both levels. Connections and fastening of the decking is not complete yet. Mechanical and electrical have resumed rough-in and stub ups at grade. Workers will be progressing through to the second floor in the next few weeks. Mechanical is continuing to install hangers for duct installation. Masonry work has commenced on site. The elevator shaft and stair B has been constructed.

 

CCRL

Structural tie-ins (welding) are ongoing.

CCRL2

Below slab electrical rough-in is ongoing.

CCRL3

Elevator shaft masonry has been completed.

CCRL 4

Electrical work above grade continues.

CCRL5

Slab on grad prep is almost complete.