Civic Centre Resource Library Update – March 20

Bookmark and Share

This week at the Civic Centre Resource Library, structural steel erection is ongoing and appears to be almost complete. Work is being done at the main entrance canopy at the southeast corner. Connection welding has commenced. Distribution of Open Web Steel Joists (OWSJ) across the beam continues. Metal decking on the first floor roofs has started at the collaboration spaces.

CCRL

Steel being erected at the main entrance canopy.

OWSJ installation is ongoing.

OWSJ installation is ongoing.

Vertical framing around roof edge is ongoing.

Vertical framing around roof edge continues.

Metal decking commenced west of the reading garden.

Metal decking commenced west of the reading garden.

Steel connections are ongoing.

Steel connections continue to be installed.

 

 

Civic Centre Resource Library Update – March 6

Bookmark and Share

Things are moving quickly at the Civic Centre Resource Library. Structural steel erection continues. Approximately 95% of the steel is installed. Connections have been tied down and bolted together. Open Web Steel Joists (OWSJ) are being distributed across the beams. Secondary steel framing around the roof edge is being installed.

roof

Secondary steel framing at the roof is being installed.

OWSJ

The Open Web Steel Joists is being installed.

CCRL

Elevator pit is protected.

CCRL

East elevation steel is in place.

CCRL

Steel work continues at the southeast main entrance.