Kleinburg Library Update

Bookmark and Share

Things are moving along at Kleinburg Library. Here’s a quick photo update of what’s happening.

Kleinburg

First floor remodel of the staff work room.

Kleinburg

Excavation for the new reading garden.

Kleinburg

A look from the lower level towards the future entrance.

Kleinburg

New windows with new trim colour.

Kleinburg

Overhang for new bottom level entrance.

 

Pleasant Ridge Library – Oct. 24 update

Bookmark and Share

Here is a quick photo update of what’s happening at Pleasant Ridge Library this week.

spray foam

Installing spray foam insulation on the interior face of the high ceiling.

Spray foam

Installing spray foam insulation at the windows.

spray foam

Installing spray foam insulation at high ceiling window areas.

blue skin

Blue skin being applied on the east wall.

blue skin

Blue skin being applied in preparation for metal panel wall.

 

 

Kleinburg Library Expected to Re-open on December 8

Bookmark and Share

KLThe renovation project at Kleinburg Library is experiencing some delays and the library is now expected to re-open on Monday, December 8 at 1 p.m.

The book drop will continue to be closed during this time. You may return your library materials to any branch of Vaughan Public Libraries or renew them online.

You can also deactivate your holds online or pick them up at Pierre Berton Resource Library. If you require assistance deactivating your holds, please contact the Service Desk.  We apologize for any inconvenience.

 

Pleasant Ridge Update – Oct. 10

Bookmark and Share

This week at Pleasant Ridge Library, the spray foam insulation have been applied to the walls, the electrical distribution panel has been installed. Workers installed the glass windows on the south and north side of the building. The framing of the exterior soffit continues.

spray foam

Spray foam insulation applied to the interior face of the exterior walls.

Electric distribution

The electrical distribution panel has been installed.

soffit

The framing of the exterior soffit continues.

Glass

The glass windows on the south wall adjacent to the existing building have been installed.

glass wall

The glass windows on the north wall at the Reading Garden entrance have been installed.

 

Pleasant Ridge Library Update – Oct. 3

Bookmark and Share

This week at Pleasant Ridge Library, workers continue to install the drywall, the glass and glazing framing. The duct work, plumbing and piping insulation wrapping as well as the framing of the soffit are in progress.

drywall

Drywall board installation.

drywall

Drywall installation - view of the corridor.

Glass

Exterior glass window framing and glass installation.

glass installation

Window glass installation in the children's area.

Soffit

Soffit framing preparation for metal wall panel.