Pleasant Ridge Library Update – September 25

Bookmark and Share

This week at Pleasant Ridge Library, the drywall installation continues, the exterior glass window framing and glass are being installed both on the side of the building and on the high wall section. The soffit framing preparation for the metal wall panel is also in progress. Stay tuned for more updates next week!

drywall

Drywall board installation

Drywall

Drywall installation

windows

Exterior glass window framing & glass installation

high wall

Window frame installation on the high wall section

soffit framing

Soffit framing preparation for metal wall panels

 

Pleasant Ridge Library Update – Sept. 19

Bookmark and Share

As of this week, the roofing work has been completed, the installation of drywall continues, and the window frames are being installed.

washroom

Drywall installation in the washroom.

window frame

All window frames have been delivered onsite.

window

Window frame installation.

frames

The curtain wall frames are onsite.

electric room

The electric room is ready for floor cutting.

Kleinburg Library Renovation – September 17 Update

Bookmark and Share

Renovations continue at Kleinburg Library.The overhang framing for the main entrance and the east entrance is in progress. The stairwell to the basement has been demolished in preparation for sealing off the entrance way. The floor and roof reinforcement throughout the library has been completed.

Main Entrance

The main entrance overhang framing is in progress.

East Entrance

The east entrance overhang framing is in progress.

West Entrance

The stairwell to the basement has been demolished.

Floor and Roof

The floor and roof reinforcement has been completed.

 

Construction Has Started!

Bookmark and Share

Great news! The construction phase of the new resource library has started.

resource libraryresource library

 

Pleasant Ridge Update – Sept. 11

Bookmark and Share

As of this week, the window frames have been installed and drywall installation is in progress. The directional boring for the electric conduit has been completed and the electric room is ready for floor cutting.

window

Window frames being installed.

Window frames installed.

drywall

Drywall installation started in the electric room.

Drywall

Drywall installation continues.

directional boring

Directional boring for electrical conduit has been completed.

 

electric

The electric room has been covered up to prepare for floor cutting.

 

Pleasant Ridge Update – Sept. 5

Bookmark and Share

As of this week, the window frames have been delivered on site, the roofing membrane installation is in progress, the window openings are being tarped and more are still happening. Here is a quick photo update.

photo 1photo 2photo 3

Pierre Berton Resource Library’s Teen Lounge is Almost Ready to Open

Bookmark and Share

Pierre Berton Resource Library’s new Teen Lounge is almost ready to open! The seats and the tables have been installed, we are just waiting for some final millwork to be done. Soon, teens will be able to enjoy this great new space just for them.

teen area

Installing lounge seats in the Teen Area.

teen lounge

Installing cushions on the lounge seats.

teen lounge

Finished lounge seats.

teen lounge

Tables have also been installed.