Renovations for Kleinburg are well underway

Bookmark and Share

Renovations at the Kleinburg Library are well under way.  The library’s collections, as well as its furniture and equipment, were all moved to storage and the builders are on site.  As of this week, the covered concrete steps to the lower level at the front of the library have been removed.  The fire and emergency stairs and the roof ladder on the north side of the building have also been removed. The ceilings have been exposed to allow access to electrical cabling and some work has been done on the floors to provide access to the plumbing.  Finally, a dividing wall at the end of the basement corridor has been removed to make way for a new entrance that will provide access to the lower floor of the library from the exterior on the east side.

Kleinburg

The library’s second floor prior to our turning it over to the construction crew.

Kleinburg

The external stairwell leading to the basement on the west side of the building is gone.

Kleinburg

The fire escape and basement stair covering have been removed from the north side.

Kleinburg

The hallway in the basement now leads all the way to the back of the building.

Kleinburg

The current view from the public service desk.

Kleinburg

The old HVAC system being taken away.

 

 

 

Pleasant Ridge Library Update – Aug. 27

Bookmark and Share

As of this week, all masonry work has been completed. Roof insulation and HVAC roof top units are being installed. Installation for the curtain wall frame and the directional boarding for electric secondary service feed are in progress.

Masonry

Masonry work has been completed.

Roff

Roofing work is in progress.

 

Pleasant Ridge Library Update – Aug. 20

Bookmark and Share

If you pass by Pleasant Ridge Library this week, you will see that a lot of masonry work has been done already. Work on the air barrier and the roofing has begun!

Aug. 20

Brick cladding installed on the west elevation.

Aug. 20

Brick cladding installed on the south elevation.

Aug. 20

Masonry work being done on the north wall.

Aug. 20

Earth spoils have been removed.

Aug. 20

Roofing work begun.

 

Pleasant Ridge Update – Aug. 13

Bookmark and Share

Construction continues at Pleasant Ridge this week and things are moving quickly.

Photo 1

Brick cladding units for masonry arrived on site.

Photo 2

Workers working on masonry scaffolding on the west side of the building.

Photo 3

Workers doing masonry work on the south wall.

Photo 4

Air vapour has been installed at the glazed wall.

Photo 5

The interior partition work has been completed.

Photo 6

The interior mechanical and electrical rough-in work continues.

Pleasant Ridge Library Update – August 1

Bookmark and Share
Pleasant Ridge Library

Parapet rough carpentry completed

Pleasant ridge library

Mechanical and electrical work at Link

Pleasant ridge library

Exterior wall substrate

Pleasant ridge library

Mechanical plumbing rough‐in

Pleasant ridge library

Duct work installation

Pleasant ridge library

Roof deck at high roof to be installed