More internal work, lighting, slatwall installation and seating, has been completed at Vellore Village Library. The entrance for both the library and the Vellore Village Community Centre are almost finished.
Vellore Village Library: June 11 Update
Progress on the highly-anticipated Vellore Village Library is increasingly noticeable. The installation of the external aluminum composite metal panels on the east, north and west elevations is nearly completed. Substantial progress has been made on ceiling works including installation of ceiling tiles and ceiling-mounted lighting systems. Painting and carpet installation have also been completed. Millwork items, such as desk and wall applications, will be installed next.
Vellore Village Library: May 25 Update
Vellore Village Library continues to take shape as countless construction projects are finished and new ones begin.
Vellore Village Library: May 9 Update
Construction activities on the library show steady progress. The most evident is the external work on the soffit and composite panel installation. Providing a shared entrance to the complex, the new vestibule is under construction. Interior work shows progress on bulkhead work as well as painting.
Activities scheduled for the next two weeks include west elevation panels installation, HVAC works, decorative suspended ceiling work, electrical wiring, spray foam in the new vestibule area, and miscellaneous drywall works.
Vellore Village Library: April 18 Update
Progress is moving steadily on the construction of Vellore Village Library. It’s easier to envision what this 8,300 square foot, hour-glass shaped library will look like when it’s finished, inside and out!
Vellore Village Library: March 6 Update
Construction activities continue at the site of the new library. Glazing installation is nearly completed as insulation, drywalling and taping work continues. Ceiling framing and hangers are well underway and preparation for ceiling work has started.
Activities scheduled for the next two weeks include framing of the structural soffit, ceiling hangers installation, completion of bulkhead framing, tile work and IT room set-up to power equipment.
New library on Villa Royale Avenue officially named
The Vaughan Public Library Board is proud to announce that the official name of the 8,300-sq. ft. library connected to the Vellore Village Community Centre will be the Vellore Village Library!
Construction steadily continues. Ninety-five percent of the curtain wall glazing has been installed. Remaining glazing and sealing is expected to be fully completed in the next two weeks. The structural exterior stud work has also been completed.
The new year brings progress with library construction at Vellore Village Community Centre
Construction activities continue to move forward at the Vellore Village Community Centre’s new library.
Winter protection has been installed allowing interior work to continue during the winter months. Metal supports, steel stud framing and curtain work is ongoing in preparation for glazing installation. HVAC and work on mechanical units has been completed. Work on electrical rough-ins above ground continues.
Vellore Village South Library: December 18 Update
Construction activities are ongoing at the Vellore Village Community Centre’s new library. Roof work and curtain wall framing are anticipated to be completed in the next two weeks, followed by curtain wall installation.
Winter protection installation on the library deck is anticipated to be installed in the coming weeks. This will ensure work activities scheduled for the interior of the building can proceed and will be protected from various weather elements.
Vellore Village South Library: November 13 Update
Construction progresses on the new library at the Vellore Village Community Centre and the facility’s hourglass shape continues to be revealed.